Activities Page Assignment Tabs in P6 Professional (Such as Predecessor or Resources or Successor Tab) Do Not Load the Assignment Window Pop-Up When Selecting the Assign or Add Button Using Multiple Screens or Previously Using Multiple Screens (Doc ID 2131358.1)

Last updated on JANUARY 30, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.3.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 15.2.3.0 and later
Primavera P6 Professional Project Management - Version 15.2.3.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
When clicking the 'Assign' button (or 'Add' button) on the any of the Activities view assignment tabs in P6 Professional (such as Predecessor or Resources, or Successor tab), the assignment window does not display. 

Note:


EXPECTED BEHAVIOR
-----------------------
When clicking the 'Assign' button on the any of the assignment tabs (such as Predecessor or Resources, or Successor tab) of the Activities view in P6 Professional, the 'assign' window should pop-up and display.

STEPS
-----------------------
The issue can be reproduced at will with the following steps (using the assign resource as example):

  1. Login to P6 Professional
  2. Open a Project
  3. Load the activities view
  4. Select an activity
  5. Select the resources tab
  6. Select Add Resource
  7. Note the issue which occurs

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms