Project Not Automatically Summarizing When Assigning a Resource in Resource Planning (Doc ID 2134343.1)

Last updated on MARCH 09, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.3 to 8.3.12.0 [Release 8.3]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.3 to 8.3.12.0 [Release 8.3]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
When a resource is assigned in resource planning the project does not automatically summarize

EXPECTED BEHAVIOR
-----------------------
When a resource is assigned in the resource planning page the project would automatically summarize.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Login to P6 web
  2. Go to 'Administer' > 'My Preferences'
  3. Under 'Resources > Resource Staffing', select "Automatically summarize project after assigning resources"

    Cause

    Sign In with your My Oracle Support account

    Don't have a My Oracle Support account? Click to get started

    My Oracle Support provides customers with access to over a
    Million Knowledge Articles and hundreds of Community platforms