Cannot Change Finish Milestones Status to Finished in Html 5 View (Doc ID 2136523.1)

Last updated on JUNE 06, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 16.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.1.0.0 and later
Information in this document applies to any platform.

Symptoms

Error trying to change Finish Milestones to finished in HTML 5 View.

ERROR
-----------------------
Unable to save changes. Failed saving data. Remaining Finish Date cannot be Null. Remaining Start cannot be Null.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Log into P6 Web.
2. Open a Project.
3. Try setting a Finish Milestone to Finished in the Status tab.
4. Notice the error.

Cause