My Oracle Support Banner

Cascade Option Not Working Properly in Manage Project Plan (Doc ID 2139207.1)

Last updated on SEPTEMBER 11, 2023

Applies to:

Oracle Fusion Project Foundation Cloud Service - Version 11.1.10.0.0 and later
Information in this document applies to any platform.

Symptoms

On : 11.1.10.0.0 version, Initiate Project

ACTUAL BEHAVIOR
---------------------

Cascade Option in project dates are not working properly

EXPECTED BEHAVIOR
-----------------------
Cascade option should work for all planned finish date of tasks and sub tasks of a project

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Project start date: 01.01.2015
    Project finish date: 31.12.2017

Project plan dates :
Manage Project Plan
End tasks has planned finish date in Jan/Febr-2015
Now, I want to Change End date for all the Task and Subtask , because my project end date change to 31.12.2018

Now, see the project plan dates.

Only Project start end date and Last task date change.
I need change for all task and subtasks. the Planned Finish Date

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.