Error In 'Transfer Budget Balances To Budget Cubes Continuously: Schedule Transfer' Child Process
(Doc ID 2143048.1)
Last updated on DECEMBER 08, 2022
Applies to:
Oracle Fusion Project Costing Cloud Service - Version 11.1.11.1.0 and laterInformation in this document applies to any platform.
Goal
On : 11.1.11.1.0 version, Manage Project Costs-Process Project Cost Transactions
Error in 'Transfer Budget Balances to Budget Cubes Continuously: Schedule Transfer' Child Process
After successfully submitting the Import and Process Cost Transactions process (automatically run after selecting "Save and Release" from the Manage Unprocessed Transactions page), two child processes are created as well. ''Import and Process Cost Transactions: Generate Output Report" (Succeeded) and "Transfer Budget Balances in Budget Cubes Continuously: Schedule Transfer," which results in an error.
The same error has happened after several different attempts.
How to avoid this ?
ERROR IN LOG FOE
-----------------------
setStreamLogging():: Stream logging is unavailable so setting to false
Master process stopped because of Exception XCC_STREAMING Profile Name does not exist.
Releasing Root AM...clean()
Releasing Root AM...streamMasterprocess
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
Submit the Import and Process Cost Transactions process (automatically run after selecting "Save and Release" from the Manage Unprocessed Transactions page),
Two child processes are created as well. ''Import and Process Cost Transactions: Generate Output Report" (Succeeded) and "Transfer Budget Balances in Budget Cubes Continuously: Schedule Transfer," which results in an error.
Solution
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Goal |
Solution |