Unchecking the "Auto Assign" Checkbox Does Not Unassign the Given Resource for the Activity in Instantis EnterpriseTrack (Doc ID 2148161.1)

Last updated on JUNE 15, 2016

Applies to:

Instantis EnterpriseTrack - Version 15.2.3.0 and later
Instantis EnterpriseTrack Cloud Service - Version 15.2.3.0 and later
Information in this document applies to any platform.

Symptoms

Unchecking the Auto Assign checkbox on the Schedule page does not unassign the Resource of the Activity

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Log into Instantis EnterpriseTrack as a User with Permission to Assign Resources to Activities for Projects on the Schedule (Roadmap) page
2. Navigate to the Project Listing page
--a. Select the Project that requires Resource Assignment
3. Navigate to the Schedule (Roadmap) page of the Project
4. Click the "Edit All" button
5. Select the "Assign All" check box under the "Auto Assign" column
6. Uncheck the "Auto Assign" checkbox for an Activity
--a. The Resource that was assigned to that activity remains and does not become "Unassigned"

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms