Project Status Display Not Correctly Corresponding With Planned Project Close Date for Projects (Doc ID 2152577.1)

Last updated on JUNE 24, 2016

Applies to:

Instantis EnterpriseTrack Cloud Service - Version 15.2.1.0 and later
Instantis EnterpriseTrack - Version 15.2.1.0 and later
Information in this document applies to any platform.

Symptoms

The Project Status does not accurately display the correct setting (1-Red), (2-Yellow) or (3-Green) in correspondence to the Planned Project Close Date for Projects

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Log into Instantis EnterpriseTrack as a User with the Permissions to view Planned Project Close Dates on the Project Listing page and Project Status
2. Navigate to the Project Listing page
3. Set the Planned Project Close Date column to a date in the past
4. The Project Status column icons for the Projects display incorrectly based on Manual Definition

Cause

Sign In with your My Oracle Support account