Scheduling Is Not Working for a Project with All Activities Marked as Finished (Doc ID 2160836.1)

Last updated on JULY 22, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.2.0.0 to 15.2.8.0 [Release 15.2]
Primavera P6 Professional Project Management - Version 15.2.0.0 to 15.2.8.0 [Release 15.2]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.0.0 to 15.2.8.0 [Release 15.2]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
While scheduling a project, after F9 is clicked the Scheduling window pops up and hangs, and the P6 Client has to be forcefully terminated.

EXPECTED BEHAVIOR
-----------------------
The scheduling should finish.


The issue can be reproduced at will with the following steps:
1. Schedule a project.
2. Press F9 while the scheduling is performed.


Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms