Fixed Units Are Not Staying Fixed (Doc ID 2171258.1)

Last updated on AUGUST 17, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.4.3.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.4.3.0 and later
Primavera P6 Professional Project Management - Version 8.4.3.0 and later
Information in this document applies to any platform.

Symptoms


ACTUAL BEHAVIOR
---------------
The Remaining Units and At Completion Units of WBS Summary activity and Level of Effort (LOE) activity increased every time when scheduling, even if no change is made.


EXPECTED BEHAVIOR
-----------------------
The Remaining Units and At Completion Units of WBS Summary activity and LOE activity should not increase every time when scheduling even if no change is made.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login to P6 Client
2. Open the issue project
3. Go to Activities tab, click F9 (schedule)
4. The Assignments Remaining Units and At Complete Units under issue activity changed.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot see correct data.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms