Actual Total Cost Doubles After Importing XML File (Doc ID 2172395.1)

Last updated on JANUARY 10, 2020

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.5.0 and later
Primavera P6 Professional Project Management - Version 15.2.5.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 15.2.5.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
When exporting a project to XML from the Web and then re-importing as a new project, the actual cost is doubled. This occurs after the project is updated with actuals, scheduled, given actual units, and store period performance is run.

EXPECTED BEHAVIOR
-----------------------
The actual cost should not double after scheduled, given actual units, and store period performance is ran.

STEPS TO REPRODUCE
---------------------------

  1. Create a new project in P6 Web.
  2. Create an Activity then Assign a resource to that activity
  3. Give the activity an Actual Start.
  4. Assign activity percent complete of 40%.
  5. Schedule project to a later date (preferably 1 or 2 weeks).
  6. Update actual units on resource. Actual cost should automatically update. (if not just give the resource assignment some actual cost, like $10)
  7. Store period performance.
  8. Export to XML.
  9. Import that project back in as a new project.
  10. Open schedule and note that actual cost has now doubled.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.