Portfolio Analysis Chart Shows Incorrect Values (Doc ID 2184797.1)

Last updated on JANUARY 30, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.3 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.3 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
The Pie Chart in the P6 web client is displaying incorrect values for "At completion labor units." This occurs on values 100 and greater if Labor units are 100h the Pie chart will display 1.0h

EXPECTED BEHAVIOR
-----------------------
Pie Chart should show the correct values for "At completion labor units."

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Log into P6 web client
2. Navigate to Portfolio
3. Select Pie Chart with "At completion labor units."
4. Issue occurs

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users are unable to see the correct values in the Pie Chart.

Changes

 The issue occurs when user environment is setup as follows: The EPPM server  is configured for English and the users web browser is configured for Protuguese/Brazil

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms