Unable To Assign Resources For Cost Budget

(Doc ID 2189609.1)

Last updated on APRIL 23, 2018

Applies to:

Oracle Fusion Project Control Cloud Service - Version 11.1.11.1.0 and later
Information in this document applies to any platform.

Goal

We have requirement wherein we have create cost budget ( financial plan type) by assigning employees, however there are only four options 'Labor, 'Material Item', 'Financial','Equipment' and Non-Labor' resources.

Is there any option wherein we can have the resource group (resource list) kind of functionality which was available in EBS-R12.

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms