Timestamp Is Published Incorrectly for SUMACTUALFINISHDATE in P6WBS Extended Schema View (Doc ID 2191654.1)

Last updated on MARCH 01, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.2.3.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.3.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
The timestamp for the SUMACTUALFINISH date field is publishing incorrectly to the P6WBS view. The timestamp is also incorrect in PROJECTX and the P6PROJECT view.

The timestamp is showing as 00:00:00 instead of the correct time as shown in P6 Web (example: 16:00:00).

As a result of this discrepancy, the SUMFINISHDATEVARIANCE in P6WBS is also incorrect. For example, it is showing 8.0h which is the difference in calendar work time between 16:00:00 (SUMBASELINEFINISHDATE) and 00:00:00 (SUMACTUALFINISHDATE) for the 8h calendar assigned to the task.

Example:
P6 Web GUI shows Finish Variance of "0" for ACTUAL FINISH vs. BL FINISH correctly when Date/Time stamp is the same for the two fields.
For the same WBS element, BIP Report shows variance of "1" day for SUMACTUALFINISH vs. SUMBASELINEFINISH. PX views in database show the SUMBASELINEFINISHDATE  was stored as  <date>  17:00:00  ,  whereas the SUMACTUALFINISHDATE  was stored as <date> 00:00:00 even though P6 GUI shows as <date> 05:00 PM


STEPS TO REPRODUCE
---------------
1. Log in to P6 and create a new project with one activity
2. Give the activity an Actual Start and Actual Finish
3. Create a baseline using a copy of the current schedule
4. Assign the baseline and select Publish for the baseline
5. Run the Global Publication jobs
6. Run project publication for this project and the BL
7. Run this query against the project / baseline

select sumactualfinishdate,sumbaselinefinishdate,sumfinishdatevariance from pxrptuser.p6wbs where projectobjectid=XXXX

You will notice that the timestamp for SUMACTUALFINISHDATE is 00:00:00 instead of the correct time such as 16:00:00.

Query Results
SUMACTUALFINISHDATE SUMBASELINEFINISHDATE SUMFINISHDATEVARIANCE
02/23/2016 00:00:00 02/23/2016 16:00:00 8

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms