Why Are the Times for Any Type of Date in P6 Web an Hour Apart in the P6 Web Versus P6 Professional?

(Doc ID 2204813.1)

Last updated on DECEMBER 05, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.4.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 8.1.0.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
The time on activity start and finish dates differs by an hour between the P6 Client and P6 Web Access.

EXPECTED BEHAVIOR
-----------------------
The time on activity start and finish dates to match between the P6 Client and P6 Web Access.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Ensure that the time is set to show on dates via user preferences.
2. Open a project in P6 Professional, go to activities.
3. Open a project in P6 Web Access, go to activities.
4. Compare the start and finish date on a like activity, the time will differ by an hour.

NOTE: The P6 Client will be showing the correct time while P6 Web Access will be an hour off.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms