The Finish Milestone Date Changes After Creating And Saving The Milestone (Doc ID 2205426.1)

Last updated on DECEMBER 19, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 16.1.1.0 to 16.2.1.1 [Release 16.1 to 16.2]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.1.1.0 to 16.2.1.1 [Release 16.1 to 16.2]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR  
---------------
In P6 Web, creating a new finish milestone activity and changing the date to a future date, then saving the finish milestone activity, results in the finish date being something different than selected.

EXPECTED BEHAVIOR
-----------------------
Expects the selected date to stay after the Save button has been clicked.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. Open empty Project
2. Create new activity (don't save it)
3. Switch Activity Type to "Finish Milestone" (don't save it)
4. Change the Finish Date to some date in the Future (don't save it)
5. Save the new activity
Result: the Finish Date changes
Expected Result: the Finish Date is not changed on save
6. Change the date again and press Save
Result: the Finish Date changes to one day before the entered date
Expected Result: the Finish Date is not changed on save
7. Change the date again and press Save
Result: the Finish Date is now correct

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms