Field Entry Limit of 10,000 for Remaining Units in Team Member (Doc ID 2210201.1)

Last updated on AUGUST 16, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 16.1.0.0 to 16.2.1.1 [Release 16.1 to 16.2]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.1.0.0 to 16.2.1.1 [Release 16.1 to 16.2]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

Unable to input a value greater than 10,000 for Remaining Units in Team Member.

EXPECTED BEHAVIOR

No limit to the entry for Remaining Units in Team Member.

STEPS

The issue can be reproduced at will with the following steps:
1. Create a new project.
2. Edit Project Preferences for Activity Owners to update the assignments remaining units and status other resource assignments on an activity.
3. Create a new activity.
4. Add an Owner to the activity that can be used to log into TM.
5. Assign a non labor and material resource to the activity. Enter 100,000 for the planned units.
6. Perform the following tasks to the activity in TM:
  a. Place an actual start on the activity.
  b. Save changes.
  c. Click Status Other Resources and attempt to modify the remaining units for the non labor and material resource to 50,000.


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms