Gantt Chart Is Not Showing the Bars for the Activities When Expanding Grouping Bands in the Activities View

(Doc ID 2216488.1)

Last updated on JUNE 06, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.2.4.0 and later
Primavera P6 Professional Project Management - Version 15.2.4.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.4.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
When expanding grouping bands in the Activities view, the Gantt chart is not showing the bars for the activities.

EXPECTED BEHAVIOR
-----------------------
The bars should be shown in the Gantt chart for each activity.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Created a WBS structure with some levels.
  2. Add some activities to each level.
  3. Group by WBS
  4. Right click and collapse all
    1. Issue 1: Now refresh. Collapse all in previous step 4 is not retained. It opens up (expands) to next level for all but for one of the band it expands to complete all levels down and shows the activity.
  5. Now collapse to some WBS, such as level 1.
    1. Issue 2: Now refresh. Observe that the collapse to in step 5 above is not retained. It opens up (expands) to next level for all but for one of the band it expands to complete all levels down and shows the activity.
  6. Collapse all. Expand manually one level
    1. Issue 3: Now refresh, Observe that the collapse to in step 6 above is not retained. It opens up (expands) to next level for all but for one of the band it expands to complete all levels down and shows the activity.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms