Total Float Not Calculating On Activities With 'As Late As Possible' Constraint

(Doc ID 2220549.1)

Last updated on OCTOBER 05, 2017

Applies to:

Primavera P6 Professional Project Management - Version 15.2.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 15.2.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.0.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
When scheduling projects, Total float is not being calculated when activities have 'As Late As Possible' constraint.

EXPECTED BEHAVIOR
-----------------------
Total float should be calculated when scheduling projects, regardless of the constraints.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Log into P6
  2. Open a project containing activities with 'As Late As Possible' constraints
  3. Schedule the project
  4. Note that the Total Float never changes

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users are not able to calculate total float for activities with an 'As Late As Possible' constraint applied.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms