Resource Usage is Different in P6 Professional Client and P6 Web

(Doc ID 2224238.1)

Last updated on JULY 13, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 16.1.4.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.1.4.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
Resource Usage is different in P6 Professional Client and P6 Web

EXPECTED BEHAVIOR
-----------------------
Resource Usage is same in P6 Professional Client and P6 Web

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login P6 Client
2. Create new project, new activities, assign resource A to the activities.
3. In Activities window, check the value (such as Actual Units) shown in Resource Usage Profile for the open project only.
4. Login P6 Web
5. Publish this same project, then go to Activities window, highlight one activity, go to Assignments tab
6. Click Assign Resource, then highlight the same resource A, click "Show Usage" button, check the value (such as Actual Units) shown in the Usage Profile, it is different from the value shown in Client.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot view resource usage data same in P6 Professional Client and P6 Web

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms