Symptoms

ACTUAL BEHAVIOR
---------------
Additional Bar with type "Percent Complete" does not show in Gantt Chart.

EXPECTED BEHAVIOR
-----------------------
Additional Bar with type "Percent Complete" should show in Gantt Chart as configured.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login to P6 Web, navigate to the Activities View and show Gantt Chart.
2. Click icon "customize view" in Standard View.
3. Navigate to tab "Bars", click "Add" button to add additional Bar with type "Percent Complete", apply the settings.
4. Check the Gantt Chart and notice that the additional Bar does not show.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot show additional Bar with type "Percent Complete".

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms