Resource Analysis View Adds Overallocated Units on Top of Total Allocated Units in the Graph

(Doc ID 2236395.1)

Last updated on APRIL 11, 2018

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.2.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 16.2.0.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR:

The Resource Analysis view of P6 Web displays the total allocation in the blue/green color, plus adds the overallocated on top in red.



EXPECTED BEHAVIOR:

The graph shows the blue/green value under the limit line and the allocated on top to equal the total allocated units.

STEPS:

The issue can be reproduced at will with the following steps:

  1. Create a new project, new resource (40hr/week limit)
  2. Add a new activity to the project and assign the resource
  3. Make sure the activity is set to start and finish within a week
  4. Set the resource assignment Planned Units to 50 (10 overallocated since 40 is the limit)
  5. Publish the project
  6. Review the Resource Analysis for the resource
  7. The details in the top section are correct (40 limit, 50 allocated, 10 over), however, the histogram graph shows 50 remaining units plus 10 overallocated units.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms