Incorrect Sort Order For Both Start And Finish Milestones By Start And Finish Columns. (Doc ID 2240402.1)

Last updated on APRIL 03, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.2.13.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.13.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
Sorting by Start Date in the P6 Web is showing a system date instead of the Finish Date for Finish Milestones in the grouping roll-up when the the Finish Milestone is the earliest Activity in the grouping.

EXPECTED BEHAVIOR
-----------------------
Start Milestones use the Start Date as the Finish Date when sorting by Finish Date and Finish Milestones use the Finish Date as the Start Date when sorting by Start Date due to Milestones being 0 duration Activities.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Create a new Project.
  2. Create 3 sibling WBS': Start MS, TD, Finish MS.
  3. Add 4 Activities: 2 Task Dependent under the TD WBS, one Start Milestone under the Start MS WBS, one Finish Milestone under the Finish MS WBS.
  4. Link the activities in the following order: Start Milestone SS to Task Dependent activity 1, Task Dependent activity 1 FS to Task Dependent activity 2, Task Dependent activity 2 FF to the Finish Milestone
  5. Schedule the Project.
  6. Group by WBS in the Classic View and take note of how the roll up values display.
  7. Group by Project and sort by Start ascending. This will show the Finish Milestone, Start Milestone, TD1, then TD2.

    Cause

    Sign In with your My Oracle Support account

    Don't have a My Oracle Support account? Click to get started

    My Oracle Support provides customers with access to over a
    Million Knowledge Articles and hundreds of Community platforms