Milestones on Standard View Gantt Chart Appear Outside the Project Dates. (Doc ID 2241709.1)

Last updated on AUGUST 08, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 16.2.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.2.0.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
In the Standard View, Start / Finish Milestone aren't represented correctly. Although the dates are calculated correctly, on the Gantt Chart they appear misplaced.

EXPECTED BEHAVIOR
All the Activities to be represented correctly in Gantt Chart - Standard View.

STEPS
The issue can be reproduced at will with the following steps:

  1. Create a new Project.
  2. Add First Activity - Start Milestone.
  3. Add Second Activity - Task Dependent.
  4. Add Third Activity - Finish Milestone.
  5. Link all Activities Finish to Start (FS).
  6. Schedule the Project.
  7. Start/Finish Activity aren't represented correctly in Standard View, they are displayed before the start of the Project.
  8. Change to the Classic View and all the Activities are represented correctly.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms