When Trying To Print Using 'Calculated Finish Date' in Specific Date Range, it Calculates the Finish Date Incorrectly.

(Doc ID 2250298.1)

Last updated on AUGUST 08, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 16.2.4.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.2.6.0 and later
Information in this document applies to any platform.

Symptoms

DESCRIPTION OF PROBLEM

----------
The P6 EPPM Page Setup panel, when using the Specific Date Range option, establishes a Finish Date that is way beyond a reasonable or applicable completion date

STEPS TO REPRODUCE
----------

  1. Open P6 Web.
  2. Go to Projects, EPS Tab.
  3. Select Page Setup - Specific Date Range.
  4. Finish date for specific range date is 2337 which doesn't exist for the Project with this date.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms