Incorrect Actual Costs Being Re-Calculated When Running Recalculate Assignment Costs in P6 Web (Doc ID 2252092.1)

Last updated on MAY 09, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.3.2.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 8.3.2.0 and later
Information in this document applies to any platform.

Symptoms

Wrong actual costs being re-calculated when running Recalculate Assignment Costs in P6 Web (Actions > Run > Recalculate Assignment Costs).

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open a project in P6 Professional client
2. From P6 client select Tools menu > Recalculate Assignment Costs
3. Result: Actual Costs calculations are correct
4. Next, from P6 Web client - Open same project (from step 1)
5. From Activities view select Actions > Run > Recalculate Assignment Costs
6. Result: some Actual Costs calculations are incorrect

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms