Symptoms

When a UDF filter is applied during Update Baseline the filter is not being honored and all activities are updated and not just the UDF filtered subset.

STEPS TO REPRODUCE:

  1. Create a Text type Activity UDF code named "UPDATE"
  2. Create a filter where UDF code value "UPDATE" contains "Test"
  3. Update the UDF value "UPDATE" for some activities with "Test"
  4. Select the following option to update the baseline: When updating Activity data, include: Activity UDF's
  5. Select the following option to update the baseline: Define Filter criteria based on UDF value contains "Test"
  6. End Result: Activities with UDF values not equal to "Test" are updated

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms