The Setting "Ask me to select each time I assign" Is Not Working in Standard View (Doc ID 2265215.1)

Last updated on AUGUST 08, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 16.2.6.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.1.6.1 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
Setting "Ask me to select each time I assign" in My preferences > Global > Resource > Resource Assignment doesn't work in Standard View.

EXPECTED BEHAVIOR
-----------------------
Can be used in Standard View the function Ask me to select each time I assign

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Open P6 Web Application
  2. Go to Administer >My preferences > Global > Resource > Resource Assignment
  3. Select Ask me to select each time I assign for When assigning a resource to an existing activity assignment.
  4. Select Ask me to select each time I assign for When a resource and role share an activity assignment.
  5. Go to Project
  6. Open Project - Activities
  7. Select one activity and assign the role
  8. Select Staff Role for role assigned and add the resource.
  9. Application don't ask "Assignment Settings" (Use the Price per unit from Resource/Assignment and Use the units per time and Overtime Factor From Resource/Assignment)

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms