P6 Pro - The Schedule Comparison Report Is Prefixing The £ Symbol With  (For Example: £) (Doc ID 2281279.1)

Last updated on AUGUST 08, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 16.2.4.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.2.4.0 and later
Primavera P6 Professional Project Management - Version 16.2.4.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------

In the Schedule Comparison application (Visualizer), the label for cost values are not correctly displayed. The currency symbol for £ is prefixed with  (i.e. £)

EXPECTED BEHAVIOR
-----------------------
The currency symbol £ should display on its own.


STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Set Regional Settings Format English (UK)
  2. Set Location UK
  3. Set default keyboard UK
  4. Administrative - Change system locale - UK
  5. Set default currency Pound Sterling for Database.
  6. Open P6 Client Application
  7. Tools -> Schedule Comparison
  8. Create new or open new layout
  9. Options select the project and baseline
  10. Select Draw Option
  11. Report are open, when are comparing the cost prefixing for currency symbol £ with Â, i.e. £

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms