ACTUAL BEHAVIOR
Constraint dates imported via XLS are flipping the Month and Day opposite of the Date Format selected in the User Preferences.

EXPECTED BEHAVIOR
User Preferences Date Format is used to determine the Month/Day or Day/Month of the importing date values.

STEPS
The issue can be reproduced at will with the following steps:

  1. Change the system date and time setting to use Day/Month/Year.
    1. Click on the time in the lower right of the computer
    2. Click 'change date and time settings..."
    3. Click 'change date and time'
    4. Click 'change calendar settings'
    5. Modify the "short date" value to dd/mmm/yy
    6. Click Apply
  2. Login to P6 Professional.
  3. Set User Preferences 'Date Format' to "Month, day, year".
  4. Export a project to XLS (with a constraint type and date already applied).
  5. Modify the constraint date = '03/04/2017 12:00 AM.
  6. Save the file.
  7. Import into P6, updating the existing project.
  8. Note that the constraint date will come in as April 3rd, not March 4th.

BUSINESS IMPACT
The issue has the following business impact:
Due to this issue, users cannot import the dates correctly.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms