PJF: How To Recalculate Burden Cost After Burden Schedule Assignment Changes At Project Level (Doc ID 2292378.1)

Last updated on JULY 31, 2017

Applies to:

Oracle Fusion Project Costing Cloud Service - Version 11.1.11.1.0 and later
Information in this document applies to any platform.

Goal

Qn1:On : 11.1.11.1.0 version, Manage Project Costs-Allocate Project Costs

Project is originally using Burden Schedule 1. Costs were imported for project and transactions are seen in Manage Expenditure Items (MEI) page. Under Financial Project Settings on Project, changed the Burden Schedule from Burden Schedule 1 to Burden Schedule 2. Choose the option 'Assign the schedule to all tasks' and save. Run Generate Burden Transactions process for this project. MEI page still shows that the burden lines are calculated using the multipliers from original Burden Schedule 1 not Burden Schedule 2.

(1) Can the burdens be recalculated for these existing expenditures using updated Burden Schedule 2?
(2) Can existing burden costs be recalculated for existing project costs after a schedule has been updated on the project?
 
Qn2:How to mark project specific transactions on Manage Expenditure Items page for re-calculate burden cost ?
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms