Project Start Dates Are Mismatched Between the Unifier Schedule Sheet and P6
(Doc ID 2300859.1)
Last updated on OCTOBER 14, 2021
Applies to:
Primavera Unifier Cloud Service - Version 15.1.0.0 and laterPrimavera Unifier - Version 15.1.0.0 and later
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
P6 and Unifier are integrated using out-of-the-box integration. After syncing the P6 project with the project in Unifier, the Start Dates for a few activities are not matching. Some projects have this problem, and others are working fine.
EXPECTED BEHAVIOR
Start Dates for all activities in every project should match between P6 and Unifier.
Cause