Goal

On : 11.12.1.0.0 version, Plan Project-Manage Project Budget

Unable to baseline budgetary control enabled 'Cost Only Budget' in Projects. When Project Manager logs-in and select to create baseline, the version updates to 'Current Working'.

Solution