Budgeted Cost Is Not Updating Automatically When the Price/Unit Value Is Set to Override and Updated in Primavera P6

(Doc ID 2307425.1)

Last updated on SEPTEMBER 19, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.0 and later
Primavera P6 Professional Project Management - Version 8.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.2.4.0 and later
Information in this document applies to any platform.

Symptoms

When using the override option to change the Price/Unit for an assignment, the budgeted cost does not change.

The issue can be reproduced at will with the following steps:

  1. Assign a resource or role to a project
  2. Select "Override" for the Rate Source value
  3. Change the "Price / Unit" value

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms