DESCRIPTION OF PROBLEM:
Prior to R16.2.x, the ability to specify a time for Beginning Timesheet Date in report settings is present. In R16.2.x+, only the date can be selected and there is no box with the time selection available like there was in previous versions, such as R16.1.

STEPS TO REPRODUCE:
1. In 16.1, set Beginning Timesheet Date in report settings, picking a calendar date and specifying a time on that date
2. In 16.2, set Beginning Timesheet Date in Run Report parameters, you can pick a date from the calendar but there is no option for time

IMPACT: Customer is unable to specify time in Beginning Timesheet Date report parameter

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms