Symptoms

ACTUAL BEHAVIOR
Users on Team Member Mobile App are unable to select more than 8 regular hours per day (settings are not checked to restrict max hours for a resource).

EXPECTED BEHAVIOR
Users are able to select more than 8 regular hours a day in Team Member Mobile App.

STEPS
The issue can be reproduced at will with the following steps:

  1. Log-in to TM Mobile App
  2. Edit Timesheets
  3. Attempt to set more than 8 hours on an activity
  4. The selection options are limited to a maximum of 8 hours

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms