XER Import Takes Long Time to Complete.

(Doc ID 2313996.1)

Last updated on OCTOBER 19, 2017

Applies to:

Primavera P6 Professional Project Management - Version 16.2.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.2.0.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
It takes more than 3 hours to Import a 100 MB XER file.

EXPECTED BEHAVIOR
-----------------------
XER Import should take shorter time.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open P6 Client.
2. Go to File, Select Import.
3. Select XER.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot Import large size of XER.

Cause