Symptoms

ACTUAL BEHAVIOR
---------------
Period Remaining Units value remains with blank Period Budgeted Units after Apply Actuals.

EXPECTED BEHAVIOR
-----------------------
Period Remaining Units value should become blank with blank Period Budgeted Units after Apply Actuals.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login to P6 Pro for EPPM.
2. Show Resource Assignment View.
3. Delete Period Budgeted Units value for a month (e.g., Oct, 2018) from both of the Resource Assignments.
4. Enter Period Budgeted Units value for another month (e.g., Nov, 2018) to both of the Resource Assignments.
5. Apply Actuals.
6. Wait for the job to complete.
7. Press F5 to refresh.
8. Check Period Remaining Units and Period Budgeted Units value for both of the months.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot view correct values.

Cause

Sign In with your My Oracle Support account