Enhancement Request: Is it Possible For Actual Start/Finish Dates to Utilize the Task Calendar For Default Times?

(Doc ID 2330499.1)

Last updated on NOVEMBER 27, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.6.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 15.2.6.0 and later
Primavera P6 Professional Project Management - Version 15.2.6.0 and later
Information in this document applies to any platform.

Goal

Is it possible for Actual Start/Finish Dates to use the activity calendar for times? Currently, if an Actual Start/Finish date is entered that differs from the date/time the activity is originally scheduled for, the times will revert to midnight rather than use the activity calendar.

Solution