Cost Rollup Not Considering Material Costs

(Doc ID 2332021.1)

Last updated on DECEMBER 13, 2017

Applies to:

Oracle Fusion Cost Management Cloud Service - Version 11.12.1.0.0 and later
Oracle Fusion Cost Management - Version 11.12.1.0.0 and later
Information in this document applies to any platform.

Symptoms

Cost-roll up not considering material costs. The material and the material overall is calculated perfectly but it doesn't sum up the material cost with the manufacturing cost and overhead.


The issue can be reproduced at will with the following steps:


1. Created Cost Scenario
2. Created Standard Cost for 2 raw parts from Manage Standard Cost UI
3. Created Resource Rate from Manage Resource Rates UI
4. Created Overhead Rate from Manage Overhead Rates UI
5. Ran Rollup costs but it ended with warning and it not considered material costs.
 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms