Activity Field "Current BL Activity Percent Complete" is Not Being Updated from Baseline

(Doc ID 2339339.1)

Last updated on JANUARY 29, 2018

Applies to:

Oracle Prime Cloud Service - Version 17.10.0.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

The "Current BL Activity Percent Complete" field for the activity does not reflect the percent complete in the baseline.

EXPECTED BEHAVIOR

The "Current BL Activity Percent Complete" field for the activity show the percent complete in the baseline.

STEPS

The issue can be reproduced at will with the following steps:

  1. Log into Prime.
  2. Load the Schedule app and select an activity.
  3. Set the Activity Status to 'In Progress'.
  4. Update the Activity Percent Complete and save.
  5. Load Baselines & Snapshots and set a baseline.
  6. Return to Schedule and check the "Current BL Activity Percent Complete" column for the activity.
  7. Note, it does not reflect the percent complete in the baseline.

 

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms