PJT: Although rates are defined, Revenue amount remains blank for a Revenue Budget in Fusion Projects for a Rate Based resource

(Doc ID 2342295.1)

Last updated on JUNE 27, 2018

Applies to:

Oracle Fusion Project Control Cloud Service - Version 11.12.1.0.0 and later
Information in this document applies to any platform.

Symptoms

On : 11.12.1.0.0 version, Plan Project-Manage Project Budget

ACTUAL BEHAVIOR
---------------
For a Rate Based resource, the system is not calculating the Revenue Budget although the Rates are defined at Planning Rates.

EXPECTED BEHAVIOR
-----------------------
Expect to see the Revenue amount calculated

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. View the Budget task 2.
2. No value under Revenue



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms