Why Does the 'Close Phase' Option on the Final Phase Gate Before Realization Change to 'Close Project' On the Schedule (Roadmap) Page?

(Doc ID 2344155.1)

Last updated on JANUARY 02, 2018

Applies to:

Instantis EnterpriseTrack Cloud Service - Version 17.2 and later
Instantis EnterpriseTrack - Version 17.2 and later
Information in this document applies to any platform.

Symptoms

With Phased Gated projects, for the final phase gate before Realization (for example Control/Verify), the Close Phase Option on the Schedule (Roadmap) Page Changes to Close Project, and then to Complete Project.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Log into Instantis EnterpriseTrack as a User who is assigned to the Project
  2. Navigate to a Project with Closed Phases
  3. Navigate to the Schedule (Roadmap) page
  4. Select 'Close Phase' button to close out the last gate prior to the final phase gate before Realization
  5. Result: The 'Close Phase' option now displays as 'Close Project' on the final phase gate before Realization
  6. Select Close Project button to close out the last gate prior to the final phase gate Realization
  7. Result: The 'Close Project' option now displays as 'Complete Project' on the final phase gate Realization

 

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms