Enhancement Request: Prime Dates In Portfolios Do Not Match Dates In Schedule

(Doc ID 2355045.1)

Last updated on FEBRUARY 19, 2018

Applies to:

Oracle Prime Cloud Service - Version 18.1 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
After changing dates for an activity, the new dates are not reflected in the Portfolios / Scorecard view

EXPECTED BEHAVIOR
The date changes for the project should reflect in the Portfolios view

STEPS

  1.  Launch Prime
  2.  Add activities to a project
  3.  Schedule the project (change the data date)
  4.  Observe the new dates on the activities
  5.  Navigate to Portfolios / Scorecard
  6.  Observe the new dates for the project do not match the activity

 

Cause