ACTUAL BEHAVIOR
---------------
Multiple projects sent to Unifier, only one project displayed in log


EXPECTED BEHAVIOR
-----------------------
Show the log file with correct job information.


STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. Login P6
2. Go to Projects, EPS, open projects to run the send to schedule sheet job.
3. Go to Activities window, run View Service Status to check the job status.
4. A batch of 20 projects had Data Exchanged and the detail displayed on the Schedule Sheet Log was for a single completely unrelated project. Also, the sender reflected is not mine.


BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot view correct log information

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms