Symptoms

On : 11.12.1.0.0 version, Manage Project Costs
Unable to assign project task to multiple assets.

 If task is top, lowest task then user is unable to assign project task to multiple assets. User is able to assign it only for one Asset.
Create Task which is top, lowest task. Assign it one Asset then try to assign it to another Asset. The TASK LOV is not showing that task.

Cause