In the Summary Payment Application, Percent Complete/Work Complete and Reverse Calculations Are Not Updating

(Doc ID 2398413.1)

Last updated on JUNE 12, 2018

Applies to:

Primavera Unifier Cloud Service - Version 18.2 to 18.4 [Release 18.2 to 18.4]
Information in this document applies to any platform.

Symptoms

On Unifier : Version 18.2

ACTUAL BEHAVIOR
-----------------------
The functionality of reverse calculation is not working between Percentage Complete to Date and Work Complete This Period.  When entering Percent Complete, the Work Complete This Period total doesn't get calculated.  It works fine the other way if you enter dollar values and then get the percent.

EXPECTED BEHAVIOR
-----------------------
When entering Percent Complete, the Work Complete This Period total should get calculated.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot get the Work Complete This Period total to calculate correctly from the reverse calculation.

Changes

 The Primavera Unifier environment was upgraded to the 18.2.0.0 version.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms