Error: "RulesException: You Cannot Enter a Remaining Finish Date for a Resource Assignment for a Completed Activity (PRM-003015036)" Attempting to Import P6 EPPM XML

(Doc ID 2405650.1)

Last updated on JUNE 22, 2018

Applies to:

Oracle Prime Cloud Service - Version 18.1 and later
Information in this document applies to any platform.

Symptoms

When attempting to update an existing schedule via a Primavera xml import, the import fails with the following error:

ERROR
-----------------------
RulesException: You cannot enter a remaining finish date for a resource assignment for a completed activity (PRM-003015036)

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Attempt to import P6 XML with schedule App
2. Import fails and error occurs in the log


 

Changes

Issue caused by product defect
 Bug 27754204 - PRM-003015036-YOU CANNOT ENTER A REMAINING FINISH DATE FOR A RESOURCE ASSIGNMENT 



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms