Work Order Completion and Work Order Job Close Cannot Be Costed And Accounted Correctly

(Doc ID 2405737.1)

Last updated on MAY 31, 2018

Applies to:

Oracle Fusion Cost Management Cloud Service - Version 11.12.1.0.0 and later
Oracle Fusion Cost Management - Version 11.12.1.0.0 and later
Information in this document applies to any platform.

Goal

After closing the WIP (Work in Progress) job, the second WO (Work Order) ends up in not getting costed due to WIP transactions unprocessed. This issue traces back to WIP material issue to get costed, accounted, but distribution processor errors showing negative inventory. Due to which, WO product completion and WO Job close cannot not be costed and accounted.

WIP material issue happens even though it drives negative inventory, but costed and accounted in Cost Distribution Processor. This means, WO product completion and WO job close also should get costed and accounted, in order to be consistent.

How to remove the constraint of WO Job Close and compute the cost of WO product completion even when the WO job is not closed?
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms