ACTUAL BEHAVIOR

When attempting to Add an Activity to the Schedule Sheet nothing seems to happen after the user enters the needed data and clicks on the OK button.

EXPECTED BEHAVIOR

A user with the applicable permission should be able to manually Add an Activity to a Schedule Sheet.

The following error can also be viewed via the Developer's Console (F12):

Object doesn't support property or method 'getMonth'

 

This issue can be reproduced at will using the following steps:

  1. Login to Unifier, navigate to the applicable work space and open the Schedule Sheet.
  2. Select the empty row where the Activity is to the added.
  3. Select Add > Manual.
  4. Fill out the required fields and click OK.
  5. Note that nothing happens.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.