Unchecking "Finished" Flag In A Finish Milestone Is Impossible

(Doc ID 2406750.1)

Last updated on JUNE 01, 2018

Applies to:

Oracle Prime Cloud Service - Version 18.4 to 18.5 [Release 18.4 to 18.5]
Information in this document applies to any platform.

Symptoms

On : NA version, Cloud: Schedule, Progress and Tasks

ACTUAL BEHAVIOR
---------------
After removing the Finished check mark above the Finished date field from a Finish Milestone, the Started date field (which does not allow manual changes) becomes null and prevents changes from being saved.

EXPECTED BEHAVIOR
-----------------------
Removal of the Finished check mark from a Finish Milestone, should not change the Started value for that milestone.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a Finish milestone
2. Set the Finished check mark for that milestone.
3. Remove the Finished check mark for that milestone and attempt to save.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, Finish milestones that have had the Finished check mark set, cannot have that status changed.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms